‘New Gwadar International Airport to be fully operational in Sept 2023’

- Advertisement -

TOP NEWS

ISLAMABAD: The Secretary of the Aviation Division has apprised the Parliamentary Committee on China Pakistan Economic Corridor (CPEC) regarding the progress on New Gwadar International Airport (NGIA) and it would be fully operational by September 2023.

The Aviation Division’s secretary informed the parliamentary committee on CPEC during a meeting held under the chair of its chairman Sher Ali Arbab today.

He stressed that Gwadar was a gateway to CPEC and undeniably important in the entire rationale behind CPEC, APP reported.

new gwadar international airport operational parliamentary committee cpec

The chairman remarked, “We have to place it at high priority therefore no effort should be spared in resolving all the outstanding issues of clean water, electricity, infrastructure and livelihoods faced by the people of Gwadar.”

The Gwadar Port Authority Chairman informed that all the efforts regarding the completion of Pak-China Technical & Vocational Institute are on the track and the project will be completed in December 2021.

Gwadar Port Authority is also consulting with NAVTTC, TEVTA and Chinese to devise a broad curriculum for the institute.

new gwadar international airport operational parliamentary committee cpec

The committee remarked that while keeping present and future skills required in view, the curriculum for the institute should be devised in a way that there must not be any gap between the skills required and offered in the institute.

The committee also directed the concerned departments to expedite the process of payments to be disbursed among the affected people of damaged houses and land acquisitions so that people of Gwadar, who are already agitating for basic amenities of life, could be compensated.

On agenda of Chashma Right Bank Canal (CRBC), D.I. Khan, Chairman, WAPDA apprised the committee that the feasibility study and the detailed engineering design of the project would be completed by March next year.

new gwadar international airport operational parliamentary committee cpec

The committee chairman remarked that the project was pivotal for the agriculture sector in Khyber Pakhtunkhwa (KP) and decided that the committee will convene special follow up meeting on the said project in February next year to ensure that the given timelines are met in letter and spirit.

The committee remarked that $1 billion grant given by China for socio-economic development projects under CPEC framework should be utilized effectively by including the projects having high social impacts and high visibility.

The committee directed the Ministry of Planning, Development and Special Initiatives to devise a comprehensive framework through which provinces may choose the projects which could bring value addition and meet true sense of socio-economic development.

The meeting was attended by MNAs Sadaqat Ali Khan Abbasi, Umar Aslam Khan, Mir Khan Muhammad Jamali, MNA, Ms. Nafeesa Inayatullah Khan Khattak, MNA, Mr. Ghous Bux Khan Mahar, MNA, Mr. Murtaza Javed Abbasi, Mehnaz Akber Aziz, Raza Rabani Khar, Zahid Akram Durrani, Senators Muhammad Tahir Bizinjo and Khalida Ateeb.